Pipeline of Renewable Energy Projects

Banana shire resources resource recovery renewable energy sites 2024 apr 15

UPDATED: October 2024


Banana Range Wind Farm

Status - Development

Proponent - EDF Renewables Australia

Location - 20km west of Biloela

Size - 450MW (Stage 1 & 2 combined)

No Turbines - 75

Battery onsite? - Yes. The project has the potential to incorporate battery storage, as part of a solar expansion stage.

Anticipated Construction Start - Q1 2026

Anticipated Construction End - Q4 2028

Anticipated Construction Duration - 36 months

Awarded Principal Contractor - To be announced at FID

Awarded Sub-Contractors - To be announced at FID

Anticipated Jobs – Construction (Direct) - 150 - 200

Anticipated Jobs – Operational (Direct) - 10 - 15

Community Benefit Fund Annual Amount (30-year period) - $100,000

Community Benefit Fund Webpage - https://www.bananarangewindfarm.com.au/community

Website - www.bananarangewindfarm.com.au

Supplier Contact - www.bananarangewindfarm.com.au/employment

Supplier Register
Local suppliers are encouraged to register their interest in providing materials or services to the awarded principal contractor (once appointed by the project proponent). The Project Proponent will make the list available to the principal contractor (once appointed). The successful principal contractormay then run its own procurement process amongst the suppliers and other entities it may wish to engage. Register at www.bananarangewindfarm.com.au/employment


Boulder Creek Wind Farm

Status - Construction

Proponent - Aula Energy/CS Energy

Location - Westwood

Size - Stage 1: 228MW
Stage 2: 144MW
Total: 372MW

No Turbines - Stage 1: 38
Stage 2: Up to 22
Total: Up to 60

Battery onsite? - No battery proposed at Boulder Creek at this time

Anticipated Construction Start - Q1 2025

Anticipated Construction End - Q4 2026

Anticipated Construction Duration - 20– 30months

Awarded Principal Contractor - DT Infrastructure

Awarded Sub-Contractors - Pending

Anticipated Jobs – Construction (Direct) - 250-350

Anticipated Jobs – Operational (Direct) - 10-20

Community Benefit Fund Annual Amount (over30-year period) - Pending

Community Benefit Fund Webpage - Pending

Website - www.bouldercreekwindfarm.com.au

Supplier Contact - info@bouldercreekwindfarm.com.au

Supplier Register
Local suppliers are encouraged to register their interest to provide materials or services to the awarded principal contractor (once appointed by the project proponent). The Project Proponent will make the list available to the principal contractor (once appointed). The successful principal contractors may then run their own procurement process amongst the suppliers and other entities it may wish to engage. Register your interest at info@bouldercreekwindfarm.com.au


Bungaban Wind Energy Project

Status - Development

Proponent - Windlab

Location - Approximately 60km south-east of Taroom

Size - 1.4GW

No Turbines / Solar Panels - Up to 204

Battery onsite? - Pending

Anticipated Construction Start - Q4 2025

Anticipated Construction End - 2029

Anticipated Construction Duration - 4 years

Awarded Principal Contractor - Pending

Awarded Sub-Contractors - Pending

Anticipated Jobs – Construction (Direct) - 600 – at peak construction

Anticipated Jobs – Operational (Direct) - 10-15

Community Benefit Fund Annual Amount (30-year period) - Pending

Community Benefit Fund Webpage - Pending

Website - https://www.southqueenslandrenewablegenerationhub.com/

Supplier Contact - sqrgh@windlab.com.au

Supplier Register
Local suppliers are encouraged to register their interest with the project team to be notified of supplier information sessions and opportunities. To register, please email sqrgh@windlab.com.au


Callide Solar Power Station

Status - Development

Proponent - Edify Energy

Location - Mount Murchinson

Size - 200MWac solar PV generator

No Turbines / Solar Panels - Pending

Battery onsite? - 200MW/800MWh battery energy storage system

Anticipated Construction Start - FY 2025/2026

Anticipated Construction End - FY 2027/2028

Anticipated Construction Duration - 24 months

Awarded Principal Contractor - Pending

Awarded Sub-Contractors - Pending

Anticipated Jobs – Construction (Direct) - 250

Anticipated Jobs – Operational (Direct) - 6-10

Community Benefit Fund Annual Amount (30-year period) - Pending

Community Benefit Fund Webpage - Pending

Website - Pending

Supplier Contact - Pending

Supplier Register
Local suppliers are encouraged to register their interest in providing materials or services to the awarded principal contractor (once appointed by the project proponent). The Project Proponent will make the list available to the principal contractor (once appointed). The successful principal contractors may then run their own procurement process amongst the suppliers and other entities it may wish to engage. Register at https://edifyenergy.com/partner-with-us/corporates


Callide Wind Farm

Status - Development

Proponent - DP Energy

Location - 22km north-east of Biloela

Size - 430 MW

No Turbines - 70

Battery onsite? - Potential for inclusion of Battery in proposed substation area

Anticipated Construction Start - Q3 2025

Anticipated Construction End - Q4 2027

Anticipated Construction Duration - 18 months

Awarded Principal Contractor - Pending

Awarded Sub-Contractors - Pending

Anticipated Jobs – Construction (Direct) - 280

Anticipated Jobs – Operational (Direct) - 30

Community Benefit Fund Annual Amount (30-year period) - Pending

Community Benefit Fund Webpage - Pending

Website - www.callidewindfarm.com.au

Supplier Contact - www.callidewindfarm.com.au/employment

Supplier Register
Local suppliers are encouraged to register their interest to provide materials or services to the project website at www.callidewindfarm.com.au The Project Proponent will make the list available to the principal contractor (once appointed). The successful principal contractor may then run its own procurement process amongst the suppliers and other entities it may wish to engage.


Kariboe Wind Farm

Status- Pre-approval

Proponent - BayWa r.e. Projects Australia

Location - 40km southeast of Biloela

Size - 1000 MW

Number of Turbines - Up to 170

Battery onsite - There will be a battery facility onsite to allow for the capture and storage of dispatchable energy.

Anticipated Construction Start - Pending

Anticipated Construction End - Pending

Anticipated Construction Duration - Pending

Awarded Principal Contractor - Pending

Awarded Sub-Contractors - Pending

Anticipated Jobs – Construction (Direct) - 400

Anticipated Jobs – Operational (Direct) - Up to 40

Community Benefit Fund Annual Amount (30-year period) - Pending

Community Benefit Fund Webpage - Pending

Website - www.baywa-re.com.au/en/wind/projects/kariboe-wind-farm

Supplier Contact - kariboe-windfarm@baywa-re.com

Supplier Register
Local suppliers are encouraged to register their interest to provide materials or services to the awarded principal contractor (once appointed by the project proponent). The Project Proponent will make the list available to the principal contractor (once appointed). The successful principal contractors may then run its own procurement process amongst the suppliers and other entities it may wish to engage. Supplier Register at kariboe-windfarm@baywa-re.com


Mount Hopeful Wind Farm

Status - Development

Proponent - Neoen

Location - Dululu/Ulogie

Size - 350 MW

No Turbines - 50 to 65

Battery onsite? - To be confirmed at a later stage

Anticipated Construction Start - Q2 2025

Anticipated Construction End - Q2 2027

Anticipated Construction Duration - 30 months

Awarded Principal Contractor - Pending

Awarded Sub-Contractors - Pending

Anticipated Jobs – Construction (Direct) - 220+

Anticipated Jobs – Operational (Direct) - 8 to12

Community Benefit Fund Annual Amount - $100,000

Community Benefit Fund Webpage - Pending

Website - www.mounthopefulwindfarm.com.au

Supplier Contact - www.mounthopefulwindfarm.com.au/workwithus

Supplier Register
Local suppliers are encouraged to register their interest as a job seeker or supplier for the construction of the Mount Hopeful Wind Farm. Neoen will provide these registration details to all tenderers during procurement. This ensures local procurement opportunities are identified early and utilised by the awarded construction contractor. Register your interest at https://mounthopefulwindfarm.com.au/workwithus/


Mount Rainbow Wind Farm

Status - Development

Proponent - Central Queensland Power (CQP)

Location - Dumgree

Size - Up to 315 MW

No Turbines - Up to 70

Battery onsite? - Pending studies

Anticipated Construction Start - Q1 2028

Anticipated Construction End - Q1 2030

Anticipated Construction Duration - 24 months

Awarded Principal Contractor - Pending

Awarded Sub-Contractors - Pending

Anticipated Jobs – Construction (Direct) - 200 to 450

Anticipated Jobs – Operational (Direct) - 15

Community Benefit Fund Annual Amount (30-year period) - Pending

Community Benefit Fund Webpage - Pending

Website - www.centralqueenslandpower.com.au

Supplier Contact - www.centralqueenslandpower.com.au/contact-1

Supplier Register
Local suppliers are encouraged to register their interest to provide materials or services to the awarded principal contractor (once appointed by the project proponent). The Project Proponent will make the list available to the principal contractor (once appointed). The successful principal contractors may then run its own procurement process amongst the suppliers and other entities it may wish to engage. Supplier Register at www.centralqueenslandpower.com.au/contact-1


Mount Sugarloaf Wind Farm (Thangool)

Status - Development

Proponent - Central Queensland Power (CQP)

Location - 16km southeast of Biloela

Size - 252 MW

No Turbines - Up to 56

Battery onsite? - Pending

Anticipated Construction Start - Q1 2028

Anticipated Construction End - Q1 2030

Anticipated Construction Duration - 24 months

Awarded Principal Contractor - Pending

Awarded Sub-Contractors - Pending

Anticipated Jobs – Construction (Direct) - 250 to 500

Anticipated Jobs – Operational - 15

Community Benefit Fund Annual Amount (30-year period) - Pending

Community Benefit Fund Webpage - Pending

Website - www.centralqueenslandpower.com.au

Supplier Contact - www.centralqueenslandpower.com.au/contact-1

Supplier Register
Local suppliers are encouraged to register their interest to provide materials or services to the awarded principal contractor (once appointed by the project proponent). The Project Proponent will make the list available to the principal contractor (once appointed). The successful principal contractors may then run its own procurement process amongst the suppliers and other entities it may wish to engage. Supplier Register at www.centralqueenslandpower.com.au/contact-1


Moura Solar Farm

Status - Operational

Proponent - Mytilineos

Location - Moura

Size - 110 MW

No of solar panels - 185,000 solar modules mounted on a single axis tracking system

Construction Start - November 2021

Construction End - August 2022

Construction Duration - 9 months

Awarded Principal Contractor - Metka EGN Australia (QLD) Pty Ltd

Awarded Sub-Contractors

  • 30/07/2021 - Sub Station Design & Construct- Yurika, QLD
  • 28/09/2021 - Fencing - My Fence Australia, QLD (business based south of Brisbane)
  • 11/10/2021 - Civil- Goldward Civil, QLD
  • 1/12/2021 - Electrical- AEC, QLD
  • 30/11/2021 - Mechanical- Pilecom, WA
  • 13/10/2021 - Site Security- SET, QLD

Jobs – Construction (Direct) - Up to 250 jobs during construction

Jobs – Operational - Four (4) operational jobs. Residential workers include a Site Supervisor, 2 Site Technicians and 1 Labourer.

Community Benefit Fund Annual Amount (30-year period) - Pending

Community Benefit Fund Webpage - Pending

Website - www.mourasolar.com.au

Supplier Contact - www.mourasolar.com.au


Sawpit Solar Farm

Status - Feasibility

Proponent - European Energy

Location - 30km south-west of Biloela

Size - 1000MW

No Turbines or Solar Panels - NA

Battery onsite? - To be confirmed at a later stage

Anticipated Construction Start - 2025

Anticipated Construction End - Pending

Anticipated Construction Duration - 12-24 Months

Awarded Principal Contractor - Pending

Awarded Sub-Contractors - Pending

Anticipated Jobs – Construction (Direct) - Pending

Anticipated Jobs – Operational - Pending

Community Benefit Fund Annual Amount (30-year duration) - Over $1m in grant funding will be available to local organisations during project operation.

Community Benefit Fund Webpage - Pending

Website - https://au.europeanenergy.com/sawpit-solar-farm/

Supplier Contact - infoaus@europeanenergy.com

Supplier Register
Local suppliers are encouraged to register their interest to provide materials or services to the awarded principal contractor (once appointed by the project proponent). The Project Proponent will make the list available to the principal contractor (once appointed). The successful principal contractors may then run its own procurement process amongst the suppliers and other entities it may wish to engage. Register your interest at infoaus@europeanenergy.com


Smoky Creek Solar Power Station

Status - Development

Proponent - Edify Energy

Location - Goovigen

Size - 800 MW

Battery onsite - Yes – anticipate 200MW/800MWh

Anticipated Construction Start - Q1 2025

Anticipated Construction End - Q1 2027

Anticipated Construction Duration - 24 months

Awarded Principal Contractor - Pending

Awarded Sub-Contractors - Pending

Anticipated Jobs – Construction (Direct) - 350

Anticipated Jobs – Operational - 10

Community Benefit Fund Annual Amount (30-year period) - Pending

Community Benefit Fund Webpage - Pending

Website - www.edifyenergy.com/project/smoky-creek

Supplier Contact - hello@edifyenergy.com

Supplier Register
Local suppliers are encouraged to register their interest to provide materials or services to the awarded principal contractor (once appointed by the project proponent). The Project Proponent will make the list available to the principal contractor (once appointed). The successful principal contractor may then run its own procurement process amongst the suppliers and other entities it may wish to engage. Supplier Register at hello@edifyenergy.com


Specimen Hill Wind Farm

Status - Development

Proponent - Ark Energy

Location - 25 km north-east of Biloela

Size - 335 MW

No Turbines - 56

Battery onsite? - To be confirmed at a later stage

Anticipated Construction Start - Q1 2025

Anticipated Construction End - Q1 2028

Anticipated Construction Duration - 3 years

Awarded Principal Contractor - Pending

Awarded Sub-Contractors - Pending

Anticipated Jobs – Construction (Direct) - 250-350

Anticipated Jobs – Operational - 15-30

Community Benefit Fund Annual Amount (30-year period) - Pending

Community Benefit Fund Webpage - Pending

Website - https://arkenergy.com.au/wind/specimen-hill-wind-farm/

Supplier Contact - info@arkenergy.com.au

Supplier Register
Local suppliers are encouraged to register their interest to provide materials or services to the awarded principal contractor (once appointed by the project proponent). The Project Proponent will make the list available to the principal contractor (once appointed). The successful principal contractors may then run its own procurement process amongst the suppliers and other entities it may wish to engage. Register your interest at info@arkenergy.com.au


Theodore Solar Farm

Status - Development (Dormant)

Proponent - juwi Renewable Energy

Location - Lonesome Creek

Size - 70 MW

Number of solar panels - Pending

Battery onsite? - Pending

Anticipated Construction Start - Pending

Anticipated Construction End - Pending

Anticipated Construction Duration - Pending

Awarded Principal Contractor - Pending

Awarded Sub-Contractors - Pending

Anticipated Jobs – Construction (Direct) - Pending

Anticipated Jobs – Operational - Pending

Community Benefit Fund Annual Amount (30-year period) - Pending

Community Benefit Fund Webpage - Pending

Website - Pending

Supplier Contact - Pending


Theodore Wind Farm

Status - Pending

Proponent - RWE Renewables Australia

Location - 22km East of Theodore

Size - 1100 MW

No Turbines / Solar Panels - Pending

Battery onsite? - Pending

Anticipated Construction Start - Q1 2026

Anticipated Construction End - 2029

Anticipated Construction Duration - 2-4 years

Awarded Principal Contractor - Pending

Awarded Sub-Contractors - Pending

Anticipated Jobs – Construction (Direct) - 200-500

Anticipated Jobs – Operational (Direct) - 20-50

Community Benefit Fund Annual Amount (30-year period) - $100,000 community sponsorship fund – per annum during the development phase of the project $500,000 community fund - per annum from commencement of construction for the lifetime of the project

Community Benefit Fund Webpage - Pending

Website - Theodorewindfarm.com.au

Supplier Contact - theodorewindfarm@rwe.com

Supplier Register
Local suppliers are encouraged to register their interest in providing materials or services to the awarded principal contractor (once appointed by the project proponent). The Project Proponent will make the list available to the principal contractor (once appointed). The successful principal contractors may then run their own procurement process amongst the suppliers and other entities it may wish to engage. Register at theodorewindfarm.com.au